SPEENERGY · Case study

N+1 standby power commissioning for a data hall.

Four 800 kVA containerised gensets paralleled with a Deepsea controller, full load-bank commissioning to 110% of rated load, and a multi-year preventive maintenance contract.

Engagement

Client
Hyperscale operator (under NDA)
Location
Jebel Ali, Dubai
Division
Strong Plant Energy
Duration
8 months
800 kVA containerised generator
kVA in parallel
4 × 800
Load-bank tested
110%
Redundancy proven
N+1

01The challenge

What the client needed.

A hyperscale operator needed N+1 standby capacity for a Dubai data hall during a phased capacity build. The requirement: paralleled containerised generators, load-bank-proven to 110% of rated load, with documented commissioning before the IT load came online.

02Our approach

How we structured it.

  1. 01Four 800 kVA sound-attenuated containerised gensets specified with Deepsea synchronising controllers, sized for N+1 redundancy.
  2. 02Pre-mobilisation factory commissioning with the synchronisation panel, isolators and switchgear pre-wired into the cabinets.
  3. 03On-site paralleling test, load step response, transient analysis and 110%-rated load-bank verification, documented in a commissioning pack signed by the supervising engineer.
  4. 04Dedicated fuel pad and bunded bulk tank with auto-transfer pumps to support extended-run testing without site interruption.
  5. 05Multi-year preventive maintenance contract written against the OEM-published intervals, with telematics-enabled service alerts.

03Equipment on the contract

What was on site.

  • 4 × 800 kVA sound-attenuated containerised gensets (50 Hz, AMF/ATS)
  • Synchronising panel with Deepsea controllers
  • Resistive load bank (commissioning + annual re-test)
  • Bulk fuel tank with bunded containment and auto-transfer
  • Distribution switchgear and PowerLock connection points

04The outcome

What it delivered.

  • N+1 redundancy proven: full load test sustained on three units with the fourth offline.
  • 110 % of rated load held for the required dwell time on each unit individually and in parallel.
  • Commissioning pack accepted on first submission — no rework cycles, no schedule slip.
  • PM contract extended into a multi-year service relationship.