SPEENERGY · Case study
N+1 standby power commissioning for a data hall.
Four 800 kVA containerised gensets paralleled with a Deepsea controller, full load-bank commissioning to 110% of rated load, and a multi-year preventive maintenance contract.
Engagement
- Client
- Hyperscale operator (under NDA)
- Location
- Jebel Ali, Dubai
- Division
- Strong Plant Energy
- Duration
- 8 months

- kVA in parallel
- 4 × 800
- Load-bank tested
- 110%
- Redundancy proven
- N+1
01The challenge
What the client needed.
A hyperscale operator needed N+1 standby capacity for a Dubai data hall during a phased capacity build. The requirement: paralleled containerised generators, load-bank-proven to 110% of rated load, with documented commissioning before the IT load came online.
02Our approach
How we structured it.
- 01Four 800 kVA sound-attenuated containerised gensets specified with Deepsea synchronising controllers, sized for N+1 redundancy.
- 02Pre-mobilisation factory commissioning with the synchronisation panel, isolators and switchgear pre-wired into the cabinets.
- 03On-site paralleling test, load step response, transient analysis and 110%-rated load-bank verification, documented in a commissioning pack signed by the supervising engineer.
- 04Dedicated fuel pad and bunded bulk tank with auto-transfer pumps to support extended-run testing without site interruption.
- 05Multi-year preventive maintenance contract written against the OEM-published intervals, with telematics-enabled service alerts.
03Equipment on the contract
What was on site.
- 4 × 800 kVA sound-attenuated containerised gensets (50 Hz, AMF/ATS)
- Synchronising panel with Deepsea controllers
- Resistive load bank (commissioning + annual re-test)
- Bulk fuel tank with bunded containment and auto-transfer
- Distribution switchgear and PowerLock connection points
04The outcome
What it delivered.
- N+1 redundancy proven: full load test sustained on three units with the fourth offline.
- 110 % of rated load held for the required dwell time on each unit individually and in parallel.
- Commissioning pack accepted on first submission — no rework cycles, no schedule slip.
- PM contract extended into a multi-year service relationship.